Categories

Subscribe to My Feed   Follow Me On Twitter   Join Me On LinkedIn   Friend Me On Facebook

What does Red, Amber and Green Mean for Your Projects?

Stop light reports are a great way to report on the status of your project to your stakeholders and they also provide a quick reporting from my team members to me at each team meeting (enabling us to reduce the time we meet!).

Let’s define (overall) what each of the colors means:

Stop light

Red (trouble): Project is at risk to miss a scheduled completion date, may be over budget or out of scope. Immediate management action required.

Amber (danger): Project may be at risk if issues are not addressed. Attention required.

Green (all good): Project is on track to meet scheduled dates

Now, let’s look at an example:

Project Status

Week of August xx, 20xx

Project Manager: Abigail Smith

Stoplight Rating

Status

AMBER

  • Schedule issues (see below for details) – 1 week behind
  • Resource constraints (see below for details) – down one resource who was pulled for another project

Risk Description: Schedule Issues: Project is 1 week behind due to difficulty in scheduling meetings with users to gather data on current applicant tracking system. Will make up 3 days by holding meetings with larger groups of users of system than initially planned. Can make up 2 days elsewhere on project.

Risk Description: Resource Constraints: Team lead pulled from project to help on another project. Expected to be gone from this project for only 2 weeks. If extends longer than 2 weeks, will have impact on schedule.

In this example, there are two issues – a schedule issue and a resource issue. There is a plan for both to be addressed. Because there is a plan in place and there is confidence that the plan will be successful to address the issues, these are “amber” rather than “red.” However – let’s assume that we find out that we cannot hold meetings with larger groups of users (schedule issue in table above), in that case, we need to go back to holding meetings with smaller groups and will not be able to make up the 3 days unless we can make those days up elsewhere. Assuming we cannot, this becomes “red.”

Now here is where I frequently see issues with stop light reports in use by many of my clients. Frequently, the client has not defined the parameters for the stop light report.  For example, at one pharmaceutical client, a multi-million dollar project appeared to be moving along nicely until a review of the project overall showed that the team members had a different perception of what it meant for a task to be amber or red than the project manager had. For example, for the project manager, a task went to red when it was 1 week overdue; for the team member, that same task would go to red when it was 4 weeks overdue (the team member was confident he could make up the time.) At that same client, some team members were unconcerned about the budget and didn’t consider cost status at all when reporting on project status – assuming, as one team member noted, “…even if I go over budget, someone is likely to come under so it all balances out.”  This led to the project manager reporting status to the project sponsors that was not accurate.

Fixing the problem

To be sure that status reports work effectively for your projects, and that everyone is looking at the status report and reporting on their tasks the same way, come to agreement on what red, amber and green means to you, your team and the key stakeholders/project sponsors.

Define parameters for red, amber and green: What does it mean if a project is in the “red?” Are you over budget by $x or by x amount of days? Have you lost key resources or have they been reassigned? You need to define (in conjunction with your team and sponsors) what it means if a project is in the “red.” You might choose to set parameters for simple to more complex projects, based on strategic impact or based on number of resources.  Same for “amber” projects – set parameters that are clear to everyone so that everyone is reporting the same way on their project tasks. Green is usually pretty clear cut!

Communicate those parameters. Once you have parameters set, communicate those parameters for reporting on project status to all stakeholders so when you update them on the project, there is no ambiguity about where the project stands. This enables for clearer communications and better management of your stakeholders overall.

Back to our client. Once we defined the parameters, communicated to all stakeholders and began reporting consistently across the board, we were able to ensure more consistency in how projects are managed and were better able to control projects across the board.

Don’t have parameters in place for your stop light reports? Take some time away from your projects today to work with your team and sponsors to put parameters in place for all projects moving forward. You’ll find your job as project manager a bit easier!