Project Scope Statement Sample Partially Completed Template
Download the Microsoft Word version
| Project Name: |
Employee Portal |
|
Project Number: |
EEPO 0010 |
|
Project Manager: |
Alice Johnston |
|
Date: |
May 4, 20xx |
|
Business case |
|
|
As the company grows, the number of individuals working virtually has increased to over 150 in the past year and a half. Additionally, virtual workers may only come into the office on average twice a month for meetings with others. Access is needed to employee paperwork, forms, and other documentation, along with the ability to communicate and share information between employee and manager. |
|
|
Objectives |
|
|
Develop an employee portal to:
|
|
|
Scope description |
|
|
The employee portal should be developed using technology already in use within the company – Microsoft SharePoint. The portal in phase 1 should provide access to all employees, but be segmented depending on employee role within the organization. The portal should provide access to the information documented above in the “Objectives” section. |
|
|
Acceptance criteria |
|
|
Phase 1 of project is complete when portal contains the components noted above and access has been provided to all employees, with access level dependent on employee role. |
|
|
Deliverables |
|
|
Microsoft SharePoint portal for use by all company employees. |
|
|
Exclusions |
|
|
Any additional components of the portal are out of scope for this project, but will be included in a list of objectives for Phase 2 of project, to be completed within 1 year of rollout of Phase 1. |
|
|
Constraints |
|
|
Application development resources are currently involved in the roll out of 2 other initiatives and will not be able to devote 100% of time to this project until after 4 – 6 months of the start. |
|
|
Assumptions |
|
|
Application development resources are well versed in Microsoft SharePoint. |
|
|
Milestones |
Date |
|
Requirements gathering |
June |
|
Phase 1 development |
July – Sept |
|
Phase 1 testing |
October |
|
Phase 1 complete |
November |
|
Pilot group rollout |
Dec – Feb |
|
Incorporate changes/recommendations of pilot group |
Feb – March |
|
Organization wide rollout |
March – April |
|
Training in application |
March – April |
|
Project Budget |
|
|
Estimated at $75,000 – $150,000 |
|